Major managed projects

Stecla Engenharia is a company operating in the field of construction management since 1998.

Expertise in Project and Construction Management it is our greatest differentiator, which allows us to be ENABLERS of ventures.

Prototyping Studio

Renovation of areas on the ground floor of the P&D Grupo Boticário building, adapting the spaces for the new Grupo Boticário Prototyping Studio area. Construction of walls, various finishes, adaptation of the sprinkler system and smoke detectors, electrical adjustments, plumbing adjustments, furniture supply.

NR10 – Phase V (SJP)

Continuing for 2023, items with priority 2, of the 70 programmed items for phase II, 35 items are for execution and the remaining items of phase II are programmed for 2024. For this year, the 35 items refer to the Dmom, Groninger 1, Groninger 2, Groninger 3, Optima, and Serac lines.

NR 12 – Phase V (SJP)

Adaptation of 8 docks at São José dos Pinhais logistics according to risk assessment prepared by CSB.

ETA + REUSE

Installation of an effluent reuse system to increase the quantity, improve the quality, and expand the use of reused water. Implementation of Phase II WTP: Treatment for cooling towers, boilers, and PW.

Semco Reactor Replacement

Replacement of the Semco reactor with a new reactor of the same current capacity, i.e., Semco with 3.5 tons and a 1-ton pre-mixer

Replacement ofinoxil / Isotec Reactors

Replacement of Inoxil and Isotec reactors with new reactors of the same current capacity, i.e., Inoxil and Isotec with a capacity of 2.5 tons and a pre-mixer of 0.5 tons.

Cream pipe replacement

Replacement of current piping with new stainless steel 316L piping, following GMP standards and ASME BPE 2022 recommendations, and a new passivation layer, thus creating a suitable surface for transport and contact with products. For execution, we will supply the filling machine with a container next to the machine to fill the tank using pneumatic pumps.

ETA phase 1

Potable water intake, storage, treatment, and distribution system for the Grupo Boticário factory in São José dos Pinhais–PR.

Logistics expansion

Construction of the new Logistics Warehouse in SJP – Phase I; New paving; Truck yard; Reorganization of the Gate 4 flow; New locker room; New Flammable materials storage; New Administrative Area for Logistics; New Cafeteria/Kitchen; Construction of the new Logistics Warehouse in SJP (current Justino and Lily) – Phase II

CPS - Health Space

With SJP's Industrial Expansion plan, we need to relocate the Health area to a location closer to the entrance, providing a more humane service, integrated with our work model and values.

Visit Schedule

Suitability of Botilabs' space for the Visit Program. The project includes the decommissioning of the
IT area and adjustments for receiving the new visit program model.

Channels

Civil adaptation of channels and containment basins at sites where polluting liquid products are used, such as fuel tanks, lubricating oil, chemical products and liquids.
flammable in general. They must be equipped with containment devices with the capacity to store any spills, avoiding contamination of the soil and water (Phase I - 2023): ETE Product Center; Diesel Passage Boxes; Data Center 1 and 2; generators.

Cafeteria

Modifications to the buffet area to add a ramp; Reconfiguration of the Dishwashing area; Changes to the Pantry, Happy Hour area, and Coffee area; General facility maintenance; Purchase and installation of new boilers; Update of electrical panels and circuits in the building.

Elevators – Cream Factory

Replacement of existing freight elevators and installation of a temporary and a permanent one; Adjustments to layouts and equipment positions on floors; Relocation of the cellophane wrapping machine; Reorganization of utility piping for Weighing and Scaling.

Industrial expansion

Architectural projects, public and complementary approvals, and preliminary services for works in SJP in 2024: Hydroalcoholic Plant Expansion, Cream Plant Renovation, support and complementary areas including accessibility, lighting, and landscaping.

Tube Filling Machine

Acquisition of filling machines to expand production. Adapted factory layout. Filling and weighing equipment included.

Unimed Paraná

Expansion of the administrative building of Unimed Paraná located on Linha Verde, in Curitiba – PR.

This corporate building, with its impressive 4,600.00 m², stands out not only for meeting the functional requirements, but also for its contribution to sustainability – the project received the LEED Platinum environmental certification.

Volkswagen - New Wing 12 - SBC

Construction of the new paint mixing building at the factory of Volkswagen in São Bernardo do Campo.

This project aims to further improve the automotive production, providing specialized facilities for the efficient preparation of paints.

Scania LPC - Vinhedo

Expansion in the logistics area of LPC Scania in Vinhedo. This expansion includes the construction of 3,500.00 m² of reinforced concrete flooring, providing a robust foundation for the efficient maneuvering of logistics vehicles.

Featuring a metal structure roof, fire prevention system, and electrical installations, this project stands out as an example of excellence in logistics infrastructure.

Renner Department Stores Distribution Center - São José

Distribution Center of Renner Stores in São José – SC, an impressive structure with 50,000.00 m² of built area.

This center is the ultimate expression of Renner's dedication to offering a efficient logistics to meet market demands.

O Boticário - DC expansion

Expansion of the Boticário Group in Registro – SP.

With the addition of a 5,000.00 m² listed shed, we now have a even more robust infrastructure for storing aerosol and ethanol-based products.

Convention Center Station

Renovation and expansion of Convention Center Station, where concert and leisure areas were transformed into offices. We created metal mezzanines, the raised floor for organization efficient electrical and logical cabling, and the modernization of the lighting system.

This revitalization covers the 7th, 8th, 9th, and 10th floors, totaling a wide area of 16,360.61 m².

Steclaweb - Management System

Stecla Engenharia has developed an exclusive construction management system following feedback from clients.